Description/Goal

Finalize design, complete bidding process, and commence construction of the N5 "Flex Lot"; participate in the Figge/DDP art study; begin development of the N4 "Urban Lounge" Lot; and continue to evaluate opportunities for a public-private partnership associated with the sky bridge plaza area.

Current Update

Construction on the N5 lot was delayed this quarter due to flooding. With floodwaters now receded, construction is expected to resume as soon as Iowa American Water completes work to relocate a water line. Construction is anticipated to be complete by fall as long as weather conditions allow.

During the flood, Canadian Pacific raise their rail line throughout the downtown by 4 to 24 inches. All rail crossings and access to the riverfront have been temporarily restored and City staff are working with Canadian Pacific on how to best mitigate the impact of the raise tracks on the Main Street Landing area permanently. 

Previous Status

The N5 lot will resume construction after floodwaters recede and is estimated to be completed in 2019. A new taskforce has been created and has their first meeting scheduled in May. The taskforce is established to recommend a final design to Council for the RAA.

Operational Pillar: Vibrant Region

Council Goal: Main Street Landing

Project Leader: Spiegel/Peterson

Target Completion: 4Q-19

Progress: 80%