Skip To Content

Menu

53rd Street Reconstruction & Widening - Brady to Eastern

Description/Goal

Develop and provide recommendations for improvements to the City's multi-modal infrastructure including bike lanes, sidewalks, shared-use paths, and the off-street trail system; this will include a DavenportGO open house with the public and a final recommendation to City Council for approval.

Current Update

Engineering staff is scheduled to send plans for the project to the Iowa Department of Transportation’s district staff for review in early August. Pending a favorable review, the project will be slated for a bid letting in December; construction will begin in the spring.

Previous Status

City staff received the draft final report from the consultant and is in the process of reviewing the document. Following the reports completion, staff will provide the document to the City Council.

Operational Pillar: Sustainable Infrastructure

Council Goal: Improve Infrastructure

Project Leader: Merritt, C. / Peterson

Target Completion: 2Q-21

Progress: 30%
Progress Bar Image