Telegraph Sewer and Resurfacing Work

Telegraph Rd Sewer and Pavement Improvement Project
Posted on 03/29/2019
Telegraph Rd Sewer and Pavement Improvement Project

03/29/19

Sewer and resurfacing work will resume on Telegraph Rd between Clark St and Elmwood Ave on Monday, April 1st.  No on-street parking will be allowed during construction to allow for one lane of travel in each direction during construction.

The project involves milling, full depth pavement repairs in a few areas, and then installation of new asphalt.  Work will be performed on one half of the street and then flip to the opposite half to accommodate one lane of travel in each direction for the duration of the project.

Access to side streets from Telegraph will be limited during construction.  Use the alternate route mapped.

The work is estimated to be complete by Friday, May 31st, 2019 pending weather and subsurface conditions.


10/11/18

 

Due to turn in weather, the Telegraph Rd sewer and resurfacing project will be paused for the winter and the road re-opened on Friday, October 12th.

The contractor has completed necessary sewer repairs in preparation for resurfacing work, and will return in March of 2019 to finish the resurfacing portion of the project.

09/21/18
On or about Wednesday, September 26th, sewer and resurfacing work will begin on Telegraph between Clark St and Elmwood Ave.  Work will begin with targeted sewer repairs in three locations along this stretch.  This work will be followed by milling, full depth pavement repair in a few areas, and then installation of new asphalt.  Work will be performed on one half of the street and then flip to the opposite half in order to accommodate one lane of travel in each direction for the duration of the project.

The work is estimated to be complete by late November.